Andes Drive Force Main Rehabilitation

Share Andes Drive Force Main Rehabilitation on Facebook Share Andes Drive Force Main Rehabilitation on Twitter Share Andes Drive Force Main Rehabilitation on Linkedin Email Andes Drive Force Main Rehabilitation link

Sept. 23, 2025, UPDATE: Crews have completed the rehabilitation of the underground pipes and have started filling some of the holes. There are 14 holes to fill, and in more than half of them, concrete must be poured in to support where the pipe bends before backfilling. Final repairs and backfilling the holes will take several more weeks to complete (late October). A professional landscaper will repair the affected yards once the pipe-related work is complete. The final task of this project is focused on the pump station itself, where extensive work is still required. The bypass that runs across Andes Drive and down Melissa Court will remain in place until all work is completed. That work is expected to last into November.

###

The City of Fairfax Public Works Department plans to rehabilitate approximately 3,700 feet of aging sanitary sewer force main along Andes Drive. The eight-inch cast iron pipe conveys wastewater from homes to the Andes Drive pump station. A liner will be installed inside the pipe to extend the usable life expectancy of the pipe. This project will require some excavation in the right of way and a temporary above-ground sewer bypass. The project will begin by June 23 and take about two months to complete.

Repairing and extending the life of critical wastewater infrastructure prevents failure, which could result in sanitary service disruptions, environmental harm, and more extensive repairs. This project follows the successful relining of the sanitary sewer force mains on Byrd Drive and San Juan Drive.

Spraying a New Pipe Liner
The city’s contractor, J. Fletcher Creamer & Son, Inc., will reline the inside of the pipe to extend its useful life expectancy. A small device pulled through the length of the pipe will spray a thin layer of epoxy that will harden and form a new lining. This method is more cost effective than full replacement and requires minimal excavation.

Pipe Interior Before ReliningPipe Interior After Relining

Minimal Excavation
The city has a maintenance easement on private property for accessing the force main. Excavation within this easement may occur to complete repairs to any section of force main pipe that cannot be lined. Some excavation in the right of way is required.

If necessary, a temporary sewer bypass will be installed to ensure residents’ wastewater service remains uninterrupted. The work may require short-term lane closures, and some areas may be coned off for several days.

Sept. 23, 2025, UPDATE: Crews have completed the rehabilitation of the underground pipes and have started filling some of the holes. There are 14 holes to fill, and in more than half of them, concrete must be poured in to support where the pipe bends before backfilling. Final repairs and backfilling the holes will take several more weeks to complete (late October). A professional landscaper will repair the affected yards once the pipe-related work is complete. The final task of this project is focused on the pump station itself, where extensive work is still required. The bypass that runs across Andes Drive and down Melissa Court will remain in place until all work is completed. That work is expected to last into November.

###

The City of Fairfax Public Works Department plans to rehabilitate approximately 3,700 feet of aging sanitary sewer force main along Andes Drive. The eight-inch cast iron pipe conveys wastewater from homes to the Andes Drive pump station. A liner will be installed inside the pipe to extend the usable life expectancy of the pipe. This project will require some excavation in the right of way and a temporary above-ground sewer bypass. The project will begin by June 23 and take about two months to complete.

Repairing and extending the life of critical wastewater infrastructure prevents failure, which could result in sanitary service disruptions, environmental harm, and more extensive repairs. This project follows the successful relining of the sanitary sewer force mains on Byrd Drive and San Juan Drive.

Spraying a New Pipe Liner
The city’s contractor, J. Fletcher Creamer & Son, Inc., will reline the inside of the pipe to extend its useful life expectancy. A small device pulled through the length of the pipe will spray a thin layer of epoxy that will harden and form a new lining. This method is more cost effective than full replacement and requires minimal excavation.

Pipe Interior Before ReliningPipe Interior After Relining

Minimal Excavation
The city has a maintenance easement on private property for accessing the force main. Excavation within this easement may occur to complete repairs to any section of force main pipe that cannot be lined. Some excavation in the right of way is required.

If necessary, a temporary sewer bypass will be installed to ensure residents’ wastewater service remains uninterrupted. The work may require short-term lane closures, and some areas may be coned off for several days.

Comments

loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
Page last updated: 23 Sep 2025, 10:32 AM